PHOTOGRAPHED USING A SONY A7RIIIAND A ZEISS BATIS 25mm LENS

THE FOUR COURTS REPAIR WORKS TO THE DOME

As keen observers along Dublin’s quays may have noted the veil of mesh and scaffolding that has been draped over the Four Courts Dome over the last few years is slowly beginning to drop.

The OPW completed the enabling, investigative and entablature repairs works to the Four Courts Dome at the end of July 2021. The scaffold that facilitated this phase of investigations and repairs will be dismantled over the court’s recess period of August and September 2021, to minimise disturbance to the Courts Service.

A further final phase of repair works is required to the decorative stone capitals which support the Dome. The investigative findings will be reviewed and works are anticipated to be be tendered in early 2022 and commence on-site in autumn 2022.

In 2011, a section of one of the capitals fell onto the roof of the Four Courts below, necessitating the installation of catch netting to mitigate the immediate risk pending the development of a programme of works to fully remediate the dangers emerging.

Limited scaffolding was placed at a number of selected points to allow the necessary access for specialists to urgently examine and report on the cause, location and extent of the structural issues, but it became evident that the full extent of works could only be established by erecting a full scaffold. This commenced in January 2015

THE FOUR COURTS 001
THE FOUR COURTS 002
THE FOUR COURTS 003
THE FOUR COURTS 004
THE FOUR COURTS 005
THE FOUR COURTS 006
THE FOUR COURTS 007
THE FOUR COURTS 008
THE FOUR COURTS 009
THE FOUR COURTS 010
THE FOUR COURTS 011
THE FOUR COURTS 012

REPAIR WORKS TO THE DOMESCOPE OF THE PROJECT

The initial scope included:

  • Scaffolding

  • Repair of the damaged capital

  • Examination of the support role of the steel support angle above the capitals and its removal/repair/replacement.

  • Repairs to gutter at the base of the dome and provision of safe maintenance access system.

  • Examination of the concrete dome, which is now over 90 years old, and preventative passive cathodic protection of part of the reinforcement of the concrete dome.

  • Once the scaffold was in place, detailed stone-by-stone analysis began. Meanwhile, the specialist cathodic protection system to the steel reinforcement of the concrete dome was installed.

Examination of the underside concrete surface found traces of the original sky blue decoration, but also found that the reinforcing steel mesh required protection. This involved the application of a new protective coating to the dome along with specialist plaster repairs and replacing the original decoration to this upper dome.

The supporting structure of the Lower Dome (the ceiling to the Round Hall) which is formed by steel trusses with a central opening allowing a view of the Outer Dome above and its plasterwork, again on steel supports, were all meticulously checked to ensure it could take the weight of the stone sections required for an initial replacement of two capitals.

Following detailed temporary works design to ensure that the capitals could be relieved of their loadbearing role without any movement of the overall structures, the intricately carved Portland Stone replacement capitals were carefully hoisted from the floor of the entrance Rotunda and out onto the scaffold. Attached photographs show a damaged capital and new replacement. The steel angle is clearly visible above each. The condition of the removed section of old capitals raised further concerns about how the load from the dome is being transferred though each capital and has led to further structural investigation to ensure the future long-term integrity and safety of the remaining capitals while retaining original historic fabric.

While this analysis was ongoing, additional maintenance and repair work was carried out such as the removal of decayed asphalt weathering details and replacement with lead, thereby allowing more of the original stonework to be again revealed.

Stone indent repairs to the Portland entablature have been completed by skilled stonemasons along the entire circumference of the dome including the removal of iron cramps originally inset into the stone that had caused cracking.

REPAIR WORKS TO THE DOMEWHAT REMAINS TO BE DONE

During the removal of the capitals, those that required immediate replacement, it became evident that the capitals were not only damaged at the edges but that the load-bearing core was also damaged.

The next phase of works now being detailed will involve the replacement of a greater number of capitals than originally envisaged, with each capital assessment in itself a separate exercise in removal, inspection and either repair or replacement depending on the structural viability of the stone core.

The steel angle above the capitals will also need to be replaced or repaired.

It is anticipated that this phase of works will be tendered in early 2022 and commence on-site in autumn 2022.

The OPW project team consisting of conservation architects, structural engineers and project administration were assisted by Harrison Goldman Independent Stone Consultants and Punch Consulting Engineers. The advice and related studies on repair mortars and structural analysis by the Graduate School of Professional Engineering Studies in TCD should also be acknowledged.

THE DOME HAS BEEN RESTORED


Commercial DisclosurePLEASE NOTE THAT LINKS BELOW MAY REDIRECT YOU TO THE AMAZON LOCATION MOST LIKELY TO SHIP TO YOUR ADDRESS

You will find links to buy products from Amazon, Google and other partners. If you click on these links, you’ll find that the URL includes a small extra piece of text which identifies that the click came from my websites. This text is an affiliate code, and it means that I get a small percentage of the money you spend if you choose to buy that product, or, in some cases, other products from the site soon after. These affiliate links help pay the costs of producing my websites and ensure that the content is free to you.

ZEISS BATIS 85mm LENS

Zeiss Batis 85mm f/1.8 Lens for Sony E Mount, Black

I HAVE THIS AND THE 135mm LENS

VERSATILE FULL-FRAME LENS: The powerful lens for the mirrorless full-frame system of Sony fulfills the highest requirements. Despite its compact design, the image meets the expectations of professional photographers. EXCELLENT RESOLUTION AND HIGH CONTRAST: Richly saturated and vivid colours are a must in the creation of lasting impressions. However, stray light within an optical system leads to a lightening of the image that is particularly noticeable in the shadows. This reduces image contrast, with the result that exposures lack contrast and appear faded. To avoid this, ZEISS combines various specially developed technologies to reduce the undesirable effects of stray light. ROBUST AND WEATHERPROOF METAL CONSTRUCTION: Thanks to features that are designed to keep out dust and spray water, the lens is perfectly suited for critical outdoor conditions. It is also designed for many years of intensive use. SMOOTH AND RELIABLE AUTOFOCUS: The design of the autofocus system requires an extremely accurate shifting of particular lens groups. The focusing system of ZEISS lenses is designed to ensure a robust and smooth-running autofocus mechanism with the best imaging performance.


YOU SHOULD ALSO CONSIDER THE 25mm LENS

MOBILE FRIENDLY PHOTO BLOG