STRAND ROAD

STRAND ROAD IN SANDYMOUNT

A Multitude of Projects, A Crescendo of Frustration

It seems the residents of Sandymount have been dealing with a series of major infrastructure projects in quick succession:

The Cycleway Trial
The ESB Interconnector
Uisce Éireann Water Mains Replacement
This constant churn of construction, road closures, diversions, and general disruption has understandably amplified the frustrations of residents. It's likely that each project, while necessary in its own right, contributed to a growing sense of fatigue and unease within the community.

Additional Impacts of the Water Mains Project

While the intention of the Uisce Éireann project - providing a more reliable water supply and reducing leakage - is undoubtedly laudable, it's important to recognise that even well-intentioned projects can have unintended consequences:

Traffic Disruption: The project's location on Sandymount Road, a key artery, would have inevitably caused significant traffic disruption during its three-month duration.
Noise and Dust: Construction sites are inherently noisy and dusty, impacting the quality of life for those living and working nearby.
Access Issues: The project may have restricted access to homes and businesses along the affected stretch of road.
A Cumulative Effect

Even though the water mains project was relatively short-lived, its impact, combined with the ongoing controversies surrounding the cycleway and the ESB interconnector, likely contributed to a sense of overwhelming disruption and a heightened sensitivity to any further changes in the area.

Conclusion

The protests on Strand Road paint a picture of a community grappling with the challenges of progress. It's a reminder that while infrastructure development is essential, it's equally important to consider the cumulative impact of multiple projects on residents' lives and to ensure their voices are heard and respected throughout the process.

Update: I decided to fact check claims about the interconnector and its impact on Sandymount:

Project Overview

The ESB Greenlink Interconnector is a proposed 500MW High Voltage Direct Current (HVDC) electricity interconnector between Ireland and Great Britain. The primary purpose of this project is to enhance energy security and facilitate the integration of renewable energy sources in both countries.

Purpose

Increased Energy Security: By connecting the power grids of Ireland and Great Britain, the interconnector will provide a more reliable and resilient electricity supply. This will be particularly important as both countries transition to renewable energy sources, which can be intermittent in nature.
Renewable Energy Integration: The interconnector will enable the two countries to share excess renewable energy, reducing curtailment and maximising the utilisation of clean energy resources.
Market Efficiency: The interconnector will promote competition and efficiency in the electricity markets of both countries, potentially leading to lower prices for consumers.
Route Selection

The proposed route for the Greenlink Interconnector is a combination of underground and subsea cables. The underground cables will run from Woodland substation in County Meath, Ireland to a landfall point at Rush North Beach, also in County Meath. From there, the subsea cables will traverse the Irish Sea to landfall at Barkby Beach in Wales, UK, and then continue underground to the converter station in Great Britain.

The selection of this route was based on extensive technical, environmental, and socioeconomic assessments. Key factors considered included:

Technical feasibility: The route needed to be suitable for the installation and operation of high-voltage cables, considering factors like soil conditions, seabed topography, and existing infrastructure.
Environmental impact: The route aimed to minimise impacts on sensitive habitats, protected species, and areas of natural beauty.
Socioeconomic considerations: The route sought to avoid densely populated areas, minimise disruption to communities, and take into account potential impacts on local businesses and tourism.
Project Status and Timeline

The Greenlink Interconnector project has received all necessary permits and approvals from both Irish and UK regulatory authorities. Construction commenced in 2022 and is expected to be completed in 2024.

Impact on Sandymount

The Greenlink Interconnector will not directly impact the Sandymount area in general. The underground cable route does not pass through Sandymount, and the subsea cables will be laid far offshore in the Irish Sea.

However, there could be some indirect impacts during the construction phase, particularly in areas close to the cable landfall points. These impacts may include temporary traffic disruptions, noise, and dust from construction activities. However, the project developers are committed to minimising these disruptions and working closely with local communities to mitigate any potential impacts.

In summary, the Greenlink Interconnector is a critical infrastructure project that will bring significant benefits to both Ireland and Great Britain. While there may be some temporary localised impacts during construction, the project is not expected to have any direct or long-term effects on the Sandymount area.

The protests in Sandymount regarding the ESB Interconnector likely stemmed from a misunderstanding or misinformation about the project's route. It is possible that initial proposals or early discussions included potential routes that would have directly impacted Sandymount, leading to concerns and protests from residents.

However, as the project progressed and detailed plans were finalised, it became clear that the chosen route would not directly affect Sandymount. The protests may have continued due to lingering concerns, a lack of updated information, or a general distrust of large infrastructure projects.

It's important to note that the final route for the Greenlink Interconnector was determined through a rigorous planning and consultation process, taking into account technical, environmental, and socioeconomic factors. While community feedback and concerns were considered during this process, it's unlikely that the protests in Sandymount directly caused a significant change in the route.

The current route, as mentioned previously, avoids densely populated areas like Sandymount and minimises potential impacts on communities and the environment.